Ready-to-build solar projects in Bulgaria

Is that Bulgarian solar project really ready to build? Check the plan, the Ministry's farmland opinion and the grid papers. The opinion is valid to the end of 2026

For sellers, buyers and funds weighing a solar project that is called ready to build. Two official pages back some of the stages. The rest is our own list.

Send us your project

50 dkafarmland area at which the application moves from the Agency to the MinistryMinistry of Energy, notice on changing the designation of farmland for a renewable plant,

2026the calendar year to the end of which the Ministry's opinion is validMinistry of Energy, notice on changing the designation of farmland for a renewable plant,

50,000 leva per MWguarantee ESO's page states for a storage site, per MWESO, connection page,

Answer in brief

On farmland, the papers come in a set order. The Ministry of Energy asks for the order approving the detailed plan and the protocol that it entered into force (Ministry of Energy, notice on changing the designation of farmland for a renewable plant, published 4 Jun 2026, read ). The grid is a second track at ESO, which lists Ordinance No. 6 of 28.03.2024 as the connection ordinance (ESO, connection page, read ). In our list a project is ready to build when both tracks end in dated papers in the project company's name and the building permit follows. The table below goes in that order. A row linked to an official page says what the page states and the day we read it. Every other row is our own list.

Your next step

You own a battery storage, solar or hybrid project

Tell us what you hold and at which stage. We share nothing without your agreement.

Send us your project

What happens to your enquiry →

The letters you will meet on the papers

  • ПУП-ПЗ: detailed spatial plan (ПУП), building plan (ПЗ): the plan whose entry into force the Ministry asks you to prove
  • ЗОЗЗ: the Law on the Protection of Agricultural Land, which Art. 24б sits in
  • ЗЕВИ: the Law on Energy from Renewable Sources; ESO lists a register under it
  • ЕСО: Electroenergien Sistemen Operator, the Bulgarian transmission system operator
  • КЕП: qualified electronic signature, which the ESO portal registration is signed with
  • дка: decare, the area unit of the Ministry's filing threshold
  • ДВ: State Gazette, where the Ordinance and its changes were published

The stages, row by row

The stages of a ready-to-build solar project in Bulgaria, in the order the file is built: each row with its basis and the date we read the source ()
StagePapers that should existWhat an official page says
Land designationFor every plot of the plant and of the cable route: the land-register extract and the designation in the plan. For each plot that is farmland, the papers in the next three rows.The Ministry of Energy writes that, where a renewable plant is needed to reach the national target, farmland counts as changed in designation once the detailed plan that provides for the plant has entered into force and a certificate is issued (Ministry of Energy, notice on changing the designation of farmland for a renewable plant, published 4 Jun 2026, read ).
Detailed plan (PUP-PZ)The order approving the draft plan and the protocol that shows it entered into force, each with its date. Check that the plan names a renewable plant on the plots you are buying.Among the documents the Ministry asks for are the order or other act of the competent body that approves the draft detailed plan, and the protocol or other act that it has entered into force (Ministry of Energy, notice on changing the designation of farmland for a renewable plant, published 4 Jun 2026, read ).
Opinion on the need for the plantThe opinion that was issued, with its date, and the application as filed. Check which office it went to and that the applicant is the project company or a person it authorised.The person who will build the plant files the application to change the designation of farmland together with the Minister of Energy's opinion that the investment is needed for the national target (Ministry of Energy, notice on changing the designation of farmland for a renewable plant, published 4 Jun 2026, read ). The dividing size is 50 dka (Ministry of Energy, notice on changing the designation of farmland for a renewable plant, ): above it the application goes to the Ministry, up to it to the Sustainable Energy Development Agency.
Date and validity of the opinionThe date on the opinion, and the date from which you expect to apply for the building permit. Put the two side by side and ask the seller what happens if the opinion has lapsed by then.The Ministry's page states that an opinion issued under Art. 24b is valid to the end of calendar year 2026 (Ministry of Energy, notice on changing the designation of farmland for a renewable plant, ). It does not say what follows after that, so ask the Ministry.
Grid: conditions and agreementESO's written opinion on the conditions and manner of connection, with the connection point it names, and the signed connection agreement if there is one. Ask for the payments made to ESO and their receipts.ESO's connection page lists Ordinance No. 6 of 28.03.2024 on the connection of sites to the electricity grids and a notice on its changes (ESO, connection page, read ). Read the version in force today before you rely on a paper issued under an earlier one.
Who holds the grid fileProof that the project company holds the registration and the applications with ESO. If an adviser filed them, the notarised power of attorney, and a written promise that it passes to you.ESO's page says how access to its information portal works: registration made by the applicant, or by an authorised person with a notarised power of attorney, and signed with a qualified electronic signature (ESO, connection page, read ).
Registers on the ESO pageWhether the project appears in either register, with proof from ESO. If the seller says yes, ask which one and since when.ESO's connection page lists two registers by title: a register under the Renewable Energy Act and a register of those wishing to connect under the temporary access scheme (ESO, connection page, read ). We read the titles only, so we cannot tell you which, if either, a given project belongs in. Ask ESO.
A battery in the same projectIf the project includes storage: proof that the guarantee was given (deposit or bank guarantee), its date, and who paid it. Ask what happens to it if you buy the company.ESO's page says that whoever runs an energy-storage site must give ESO a guarantee within three months of receiving its opinion on the conditions of connection, under Art. 84a of the Ordinance: 50,000 leva per MW (ESO, connection page, ) Earlier value: 50,000 leva per MW (). The page speaks of storage sites only, not of solar plants.
Connection point and free capacityThe name and voltage of the substation the connection names, and the date on which you looked it up on ESO's map.Our own list. ESO publishes a map of free capacity for connection (ESO, free capacity for connection, read ); look the substation up yourself and write down the date, because we do not read the map.
Building permitThe permit, its conditions, the date any appeal period ended and the date it stops being valid. Check that the capacity and layout in it match the grid papers.Our own list. We cite no official page for it: none of the pages we read states what a permit for a solar plant must contain.
Design and open conditionsThe technical design, and a list of every condition in the permit and the grid papers that still has to be met before construction can start.Our own list. We cite no official page for it.
Company and what is for saleThe shareholder register of the project company, its debts and pledges, and written confirmation that every share is for sale and that every paper above is in the company's name.Our own list. We cite no official page for it.

We name no price, yield or rent. None of the pages we read states one.

Three dates to line up

  • The date on the Ministry's opinion, against the end of its validity.
  • The date ESO issued its opinion on the conditions of connection, against any deadline written in it.
  • The date the building permit stops being valid, against the day you plan to start construction.

A paper without a date is a gap. Write “missing” in the middle column where one is, and read the sourced rows at their source: the link opens the page we read, and it may have changed since.

Selling a solar project?

A buyer reads your file against these rows. Arrange it in this order and mark what you do not hold yet.

Send us your project

Buying one?

Tell us the sizes, regions and stages you can act on. We list no projects.

Tell us what you want to buy

Where the list stops

The two official pages we cite are a Ministry notice about farmland and an ESO page about connection. Neither defines “ready to build”, and we do not define it on their authority. For anything that decides money, ask the Ministry, ESO, the municipality and a Bulgarian lawyer.

Written by A. Manchev EOOD, Sofia. What happens to your enquiry is in the privacy notice.

Questions and answers

What does “ready to build” mean in Bulgaria?

We cite no official definition. In our list a project is ready to build when every row above is filled with a dated paper in the project company's name and no condition is still open.

Does the Ministry's opinion make the land buildable?

No. The Ministry's notice describes the opinion as one of the documents that goes with the application to change the designation of farmland. It says nothing about a building permit or the grid.

Do you publish prices, yields or project listings?

No. We cite no price or yield because no page we read states one, and we list no projects. If you send us a project, a fee is agreed in writing before any names are shared.

Sources and as-of dates

  1. Ministry of Energy, notice on changing the designation of farmland for a renewable plant: me.government.bg, retrieved .
  2. ESO, connection page: eso.bg, retrieved .
  3. Ministry of Energy, notice on changing the designation of farmland for a renewable plant: me.government.bg, retrieved .
  4. ESO, connection page: eso.bg, retrieved .
  5. ESO, connection page: eso.bg, retrieved .